Until recently, policies aimed at cutting building emissions focused almost entirely on operational carbon, the energy a building uses once it is running. The emissions tied to manufacturing, transporting, and installing materials were left out.
A growing number of states and cities now require project teams to quantify them. Some of these rules set emissions limits, while others, including those in Washington and Boston, only require teams to report the numbers.
California: Embodied Carbon in the Building Code
California builds embodied carbon into its green building code. Under section 5.409 of CALGreen, embodied carbon requirements became mandatory on July 1, 2024 for large nonresidential projects. Projects can comply through a prescriptive path, using EPDs for materials that fall under set global warming potential (GWP) limits, or a performance path, completing a whole building life cycle assessment (WBLCA) that shows at least a 10 percent reduction in GWP from a reference baseline building.
For newly constructed buildings, the threshold was a combined floor area of 100,000 square feet when the rule took effect. For projects under the Building Standards Commission, the threshold drops to 50,000 square feet on January 1, 2026.
Public works carry a separate obligation. The Buy Clean California Act requires EPDs showing that eligible materials meet limits set by the Department of General Services. The current limits took effect January 1, 2025, with the next update due January 1, 2028.
Public Procurement: Colorado and Washington
Colorado’s Buy Clean Act covers state public projects costing more than $500,000 where the solicitation went out on or after January 1, 2024. The Office of the State Architect sets a maximum GWP for each category of eligible material. Separately, jurisdictions that update any building code after July 1, 2026 must adopt the state’s Model Low Energy and Carbon Code. The Colorado Energy Office describes that code as built on the 2024 IECC, while low carbon building materials appear in a voluntary Model Green Code.
Washington chose reporting first. Under HB 1282, covered state-funded projects over 50,000 gross square feet must submit quantities and current EPDs for structural concrete, reinforcing steel, structural steel, and engineered wood. The duty starts July 1, 2025 for projects above 100,000 gross square feet and reaches every covered project on July 1, 2027. Data must cover at least 90 percent of the cost of each covered product, and the contractor is not required to verify what suppliers provide. The statute sets no GWP limits.
Local Rules: Boston and Its Neighbors
Cities are moving too. Since July 1, 2025, Boston’s amended Article 37 has required embodied carbon life cycle assessment reporting for Large Projects over 50,000 square feet. The Massachusetts council report adds that Cambridge and Newton have adopted similar zoning rules.
At the state level the same council recommends EPD and quantity reporting for state-managed projects by mid-2027, GWP thresholds in 2028, and a WBLCA for buildings of 20,000 square feet or more. Those are recommendations, not enacted requirements.
Why the Numbers Need Context
Reporting only helps if the figures can be compared, and peer-reviewed work suggests that is not guaranteed. A review in Environmental Research Letters found published building LCA results ranging from 0.03 to 2.00 tons of greenhouse gas emissions per unit of gross area, even for similar buildings. A study in Buildings found that two widely used software and database combinations differed by about 15 percent on whole-building climate impact.
The baseline method has its own weakness. The Massachusetts council notes that an overdesigned baseline building can make a reduction easy to claim under today’s limited guidance.
The council adds that standards now in development, such as ASHRAE 240P, may improve the validity and comparability of WBLCA over the next two to five years.